Commissioning of hydropower plant Lawe Sikap

 

We are particularly pleased to announce that another “Water-to-Wire” project in South East Asia has been planned, equipped and successfully commissioned by Geppert.

The plant, consisting of two Geppert Francis turbines, has a total capacity of approx. 7.7 MW.

In addition, the power plant is capable of island operation and can almost completely supply the nearby city with green electricity in the event of a blackout.

Technical data

  • Turbine type: Francis Turbine
  • Quantity: 2
  • Location: Indonesia
  • Year of construction: 2018
  • Net head: 135 m
  • Flow rate: 6,200 l/s
  • Output per unit: 3,840 kW
  • Total output: 7,680 kW

Scope of delivery: 2 x Francis turbine, generator incl. bearing lubrication unit and water cooling, distribution piping, main shut-off device, hydraulic power unit, automation and control technology, medium-voltage switchgear, main and self-consumption transformer, emergency power supply and indoor crane.

Technical data